dc.contributor.advisor | Chuquimia Hurtado, Arturo | |
dc.contributor.author | Huanaco Romero, Zul Maryoly | |
dc.contributor.author | Rodríguez Arroyo, Luis Felipe | |
dc.date.accessioned | 2023-08-18T19:56:01Z | |
dc.date.available | 2023-08-18T19:56:01Z | |
dc.date.issued | 2023-03-31 | |
dc.identifier.uri | https://hdl.handle.net/20.500.12557/5624 | |
dc.description.abstract | El objetivo principal de la presente investigación fue realizar un estudio del trabajo el cual
pueda dar solución a aquellos elementos que inciden en la baja productividad, la aplicación
de sus técnicas ayudara a superar demoras, tiempos improductivos, ineficientes métodos de
trabajo, por lo que el interés del trabajo de investigación radica en intentar incrementar la
productividad y proponer un mejor método de trabajo. El estudio se desarrollará en la planta
de producción y se enfatizará los procesos manuales ya que la empresa trabaja de forma
semiautomatizada.
Se utilizo la metodología para seguir los pasos del estudio de métodos, describiendo la
situación actual y mejorando las actividades del proceso para lo cual se utilizaron
instrumentos como la observación directa diagramas de operación, análisis y recorrido del
proceso. Asimismo, para la medición del trabajo se cronometro cada una de las etapas y
con ayuda de la tabla de la General Electric hallamos el número de observaciones que se
debe realizar, se tomó estas observaciones como muestra, se valorizo, se añadió los
suplementos para hallar el tiempo estándar y así poder analizar el desempeño de los
operarios.
Con esta propuesta se logro se incrementar la productividad total en un 38.96% de 231 und/
hora a 321 und/ hora ya que se pudo mejorar los métodos de trabajo y con la medicion del
trabajo pudimos obtener los datos para poder comprobar con una simulación utilizando el
software ProModel que el proceso productivo se redujo 12 días 16horas 49 minutos y 36
segundos generando una reducción de 5.8% de horas trabajadas. | es_PE |
dc.description.abstract | The main objective of the present investigation was to carry out a study of the work which
can provide a solution to those elements that affect low productivity, the application of its
techniques will help to overcome delays, unproductive times, inefficient work methods, for
which the The interest of the research work lies in trying to increase productivity and propose
a better working method. The study will be carried out in the production plant and manual
processes will be emphasized since the company works semi-automated.
The methodology was used to follow the steps of the study of methods, describing the current
situation and improving the activities of the process, for which instruments such as direct
observation, operation diagrams, analysis and process route were used. Likewise, for the
measurement of the work, each of the stages was timed and with the help of the General
Electric table we found the number of observations that must be made, these observations
were taken as a sample, they were valued, the supplements were added to find the standard
time and thus be able to analyze the performance of the operators.
With this proposal it was possible to increase the total productivity by 38.96% from 231
units/hour to 321 units/hour since it was possible to improve the work methods and with the
measurement of the work we were able to obtain the data to be able to verify with a simulation
using the ProModel software that the production process was reduced by 12 days 16 hours
49 minutes and 36 seconds, generating a 6.4% reduction in hours worked. | en_US |
dc.format | application/pdf | es_PE |
dc.language.iso | spa | es_PE |
dc.publisher | Universidad Andina del Cusco | es_PE |
dc.rights | info:eu-repo/semantics/openAccess | es_PE |
dc.rights.uri | https://creativecommons.org/licenses/by-nc-nd/4.0/ | es_PE |
dc.subject | Estudio de métodos | es_PE |
dc.subject | Estudio de tiempos con cronometro | es_PE |
dc.subject | Tiempo normal | es_PE |
dc.title | Estudio del trabajo para incrementar la productividad de la línea de producción de ladrillo súper king kong en la Empresa Latesa S.A.C, Cusco, año 2019-2021 | es_PE |
dc.type | info:eu-repo/semantics/bachelorThesis | es_PE |
thesis.degree.name | Ingeniero Industrial | es_PE |
thesis.degree.grantor | Universidad Andina del Cusco. Facultad de Ingeniería y Arquitectura | es_PE |
thesis.degree.discipline | Ingeniería Industrial | es_PE |
dc.publisher.country | PE | es_PE |
dc.subject.ocde | https://purl.org/pe-repo/ocde/ford#2.11.04 | es_PE |
renati.advisor.dni | 23930267 | |
renati.advisor.orcid | https://orcid.org/0000-0002-4556-2264 | es_PE |
renati.author.dni | 72807665 | |
renati.discipline | 722026 | es_PE |
renati.juror | Benavides Palomino, Carlos Alberto | |
renati.juror | Cabrera Márquez, Sara | |
renati.juror | Blanco Velasco, Jesús Raúl | |
renati.juror | Echegaray Castillo, Tania Karina | |
renati.level | https://purl.org/pe-repo/renati/level#tituloProfesional | es_PE |
renati.type | https://purl.org/pe-repo/renati/type#tesis | es_PE |
dc.description.lineadeinvestigacion | Diseño y gestión de Sistemas de producción | es_PE |